Identifying and Evaluating Factors Affecting Contractor Selection using a Combination of Construction Management Perspectives and Multi-criteria Decision-making Methods

Document Type : Research Paper

Author
M.Sc., Faculty of Engineering, Islamic Azad University, Khomeinishahr, Isfahan, Tehran
Abstract
Contractor management, evaluation, and selection are essential parts of the construction process, as contractors are the fundamental pillars of civil and non-civil projects and the main factor in converting resources into the final product. Basically, the method of selecting contractors is based on the lowest bid price, but it is clear that numerous quantitative and qualitative indicators with different degrees of importance are considered in determining the qualification of a contractor and should be considered in decision-making. In this study, in addition to identifying the indicators affecting the selection of contractors in the Islamic Revolution Housing Foundation of Isfahan Province, the importance and prioritization of these indicators are determined using models derived from the Multi-Criteria Decision Making (MCDM) method in group decision-making. In this study, first, the research factors were identified and approved by experts in a case study, then the research factors were weighted using the AHP method, and finally, 5 contractors were ranked using the TOPSIS and VIKOR methods. According to the findings of this study, respondents have given a high rating to management criteria in selecting a contractor. This indicates that respondents consider many of the shortcomings that occur in projects to be due to management weaknesses. For example, lack of management weaknesses leads to a lack of skills in dealing with financial risks, and lack of management and its policies lead to inadequacy of policies for hiring specialized human resources, and lack of proper management also causes the manager to be unable to provide appropriate solutions to critical situations and sanctions, and projects face long-term delays and ultimately failure.
Keywords

Copyright ©, Mehrdad Hemmasian Etefagh

 

License

This article is released under the Creative Commons Attribution (CC BY 4.0) license. Anyone is free to copy, share, translate, and adapt this article for any purpose, whether commercial or non-commercial, as long as proper citation is given to the authors and original publication.

Banaitiene, N. Banaitis. A. 2006,"Analysis of Criteria for Contractors qualification Evaluation" Technological and Economic Development of Economy, 74, p. 276-282 2.
Russell. J.S. Skibniewski, M. J, 1988, "Decision criteria in contractor prequalification" Journal of Management in Engineering.Vol.4, No.2,pp.148-164.
Bapiri, Soheil, Mohammad Hosseini Germany; Alireza Alizadeh and Seyed Mojtaba Aran, 2015, Evaluation and ranking of construction project contractors based on the combined approach of FQFD and FMCDM, 11th International Conference on Project Management, Tehran, Aria Industrial Research Group.(In Persian)
Regulations for classification and qualification of contractors / Deputy for Technical Affairs / Office of Consultants and Contractors / May 2007. (InPersian)
Palaneeswaran. E. Kumaraswamy, M. 2001, "Recent advances and proposed improvements in contractor prequalification methodologies". Building and Environment 36. P.73-87
Wang. W. Wang, H. Lai, Y. Li, C, 2006, "Unit-price-based model for evaluating competitive bids" Intemational Journal of Project Management, 24, p.156-166.
Ilker Topcu.Y, 2004, "A Decision Model Proposal For Construction Contractor Selection In Turkey ,Building and Environment 39, p.469-487.
Asgharizadeh, Ezatollah and Nasrollahi, Mehdi, 2008, Identifying and determining the weight of effective indicators in selecting contractors for construction projects, Journal of Management Research, No. 2. (In Persian)
Diani, Mina and Shirviehzad, Hadi, 2012, Evaluation and selection of the best contractor in Isfahan Municipality Deputy of Civil Engineering using AHP method, the first National Conference on Industrial and Systems Engineerin.
Volume 2, Issue 2 - Serial Number 3
Serial No. 3, Summer Quarterly
Summer 2022
Pages 105-121

  • Receive Date 03 August 2022
  • Revise Date 01 September 2022
  • Accept Date 05 September 2022
  • First Publish Date 05 September 2022
  • Publish Date 23 August 2022